Building Control - Notice of Demolition

Section 80 of the Building Act 1984 requires that no person shall begin demolition unless

(a) They have given the local authority notice of their intention to do so, and
(b) either
(i) the local authority have given notice to them under Section 81 of the Building Act 1984, or
(ii) six weeks have expired from the submission of the notice.

NOTE TO APPLICANT
This notice must be completed and submitted to Winchester City Council, who upon receipt, will arrange for the Building to be inspected and a notice served on you under Section 81 of the Building Act 1984.

Demolition work must not commence until you receive the Notice or until the expiry of six weeks from your notification, whichever is the earlier.